THE 37254 FUND

OFFICIAL WEBSITE

 

uat_w
254groupfotweb
2end2ndmanscabside_1

March

Sunday 5th was the first working party of the month. Alan, Doug, Joan and Chris were on site engaged in various tasks. Alan completed the building of the cover over the lubricating oil priming pump - this time the newly-constructed backets were fitted to the cover and fully assembled. All the parts of the cover fitted together perfectly and all that remains to be done is for the cover to be painted. Alan also continued with the cleaning of the fanroom to bring it up to a standard so that it can be painted. Doug worked in the engine room cleaning yet more of the area under the floor. Joan cooked the usual super lunch and after lunch, Joan helped Chris with building the new floor for Number 2 Cab. By the end of the day, the first piece of floor had been laid down and the second piece was partly cut out.
Saturday 11th saw Chris on site for the afternoon. Chris continued with the new floor for Number 2 Cab. 5 more floor panels were cut out and laid down during the afternoon (in between the odd snow shower). Only 5 more floor panels to go!
Sunday 12th saw almost all of the floor completed in Number 2 Cab by Chris and Adrian. There are only two small pieces left to make. Adrian cleaned-out and re-tapped the holes in the floor's crossmembers when he wasn't helping Chris with cutting the floorboards. Alan continued cleaning the fan room ready for its repaint. Dan and Chris McNaughton arrived at the end of the day and helped Alan and Chris dismantle one of the spare brake cylinders so that the seals can be replaced.
On Friday 17th. Alan and Doug travelled up to Rotherham in a hired lorry to collect the majority of the spares that C.F. Booth had removed from locomotives for us. Dan met up with Alan and Doug to finalise the details. Doug and Alan brought the spares back South ready for unloading on Saturday.
Saturday 18th was the first day of a busy weekend. Alan brought the lorry down to the site for unloading which was achieved with a telescopic forklift hired from a local company. The lorry was unloaded and the stores re-palletised and then stuck into store. Adrian was on hand to assist Chris and Alan with the unloading. Once the lorry had been unloaded, Chris and Adrian commenced preparing the ground ready for the bufferstop to be put in place on the Sunday.
Sunday 19th was even more hectic than the Saturday. Alan, Doug, Joan and Chris were kept very busy on site until about 7 o'clock in the evening - we'll be doing night shifts next! Alan removed the head from the newly delivered spare compressor to get it ready for exchanging with one off of one of the compressors currently on the loco. Joan cooked the usual superb lunch which was very important as everybody was working flat out all day. In the morning, Alan and Chris re-aligned the track to take out a couple of kinks where a couple of panels have been lifted out and then dropped back in by a crane. One panel was then lifted and packed with ballast. One rail was removed from the trackpanel at the current end of the track. This rail is longer than the partner rail on the same trackpanel. When we can borrow the railsaw again, we'll cut this rail to length and then re-install it on the sleepers. In the afternoon, everyone was involved in building the bufferstop. Chris graded the trackbed with the forklift's bucket attachment. Once the trackbed had been smoothed-out, sleepers were laid down and the first part of the bufferstop was craned into place and then secured. After the first part had been secured, everyone went for tea whilst Chris did a couple of forklifting jobs for two of the other preservationists on the site. After tea, the second part of the bufferstop was dropped into place on the sleepers. The second part was trickier than the first as the rail had a slight bend in it. The bufferstop was completed shortly before it started to get dark. All that remains to complete the bufferstop is the wooden block to go between the two uprights and also fit some new double chairs to secure the rails. The test track is now 95% complete and looks like a real railway.
Friday 24th saw John and Alan working on the loco. John had changed the distributor and he and Alan tested the brake system to see if it had improved matters. The brake system is greatly improved over what it used to be like. John and Alan took the loco on a test run down the test track to a position about 20 yards short of the newly installed bufferstop.
Sunday 26th had just Alan and Chris on site for a rather wet working party. Chris secured two floor panels in Number 2 Cab and re-tapped numerous holes in the floor supports. Alan commenced removing the head of one of the compressors on the loco to try and cure a fault that had occured recently. Chris and Alan removed the head and then swapped various parts with parts on the spare compressor head to make an exact replica of the setup which was previously installed. Putting the bits back in the nose of the loco took quite a while and of course the heavens opened and both workers got drenched!

Items_-_including_Alan_s_bicycle_-_on_the_lorry[1]
17th_March_2006[1]._027
New_Floor_2